Scope
  • Refacing concrete wing walls and abutments, and replacing a 59 ft steel girder bridge.

  • Began this project with the role of general labourer, installing rebar and setting up concrete forms. After 3 months, promoted to foreman of the job site due to my strong ability to lead the team, interpret engineering drawings, and problem-solve when errors arose.

Skills
  • Problem-solving
  • Team leadership
  • Interpreting engineering drawings
  • Attention-to-detail